Magnolia Residences, Summerlin Banyo –
Construction Update – July 2019

July 2019

Magnolia Residences construction is progressing well, and we achieved the following milestones since the last update:

• In the basement, electrical and plumbing works are now complete and the mechanical exhaust system is 50% complete.
• On the ground level, the electrical and plumbing rough ins are complete with windows and gyprock due to be installed next.
• Level one has had its formwork stripped. Wall partitions have been installed and plumbing and electrical rough ins are well underway.
• Level two is currently a no-go zone as the formwork for the third floor is currently being stripped out.
• The third level slab has been poured and blockwork is nearing completion on this level.
• Once block work is complete to level three, we should see roof construction commence.

If you have already chosen to call Summerlin home, it won’t be long before we’ll be making you feel welcome. In the meantime, please be aware, Magnolia Residences remains a construction site. Therefore, for your safety, you must only access the site with prior consent and in the presence of a Summerlin representative.

CLICK HERE TO LEARN MORE MAGNOLIA RESIDENCES

SHARE WITH FRIENDS BY CLICKING BELOW
Share

SUBSCRIBE TO RECEIVE VIP EARLY ACCESS TO OUR DEVELOPMENT LAUNCHES

"*" indicates required fields

We respect your privacy and your personal information will be maintained in accordance with our "Privacy Policy", by clicking submit you agree to this policy.
This field is for validation purposes and should be left unchanged.